Update on Cultybraggan – January 2024
Our hut at #Cultybraggan is evolving fast and it’s exciting to see its progress!
The electritian has been in and the kitchen is now all in except for the plinth and the breakfast bar – which will go in once the window has been fitted.
The wiring has also been started throughout the building.
The bathroom floors were leveled over the weekend so that the rest of the bathroom fixtures can be fitted. All the interior doors have been hung and the External doors were painted last week.
This week the plan depending on the weather will be to get the walls painted that have already been plastered, hang the external doors, put the cupboard in the staff room and for the wiring to continue.