Update on Cultybraggan – January 2024

Our hut at #Cultybraggan is evolving fast and it’s exciting to see its progress!

The electritian has been in and the kitchen is now all in except for the plinth and the breakfast bar – which will go in once the window has been fitted. 

The wiring has also been started throughout the building. 

The bathroom floors were leveled over the weekend so that the rest of the bathroom fixtures can be fitted. All the interior doors have been hung and the External doors were painted last week.      

This week the plan depending on the weather will be to get the walls painted that have already been plastered, hang the external doors, put the cupboard in the staff room and for the wiring to continue.  

𝐹𝑜𝑙𝑙𝑜𝑤 𝑢𝑠 𝑡𝑜 𝑟𝑒𝑐𝑒𝑖𝑣𝑒 𝑡ℎ𝑒 𝑙𝑎𝑡𝑒𝑠𝑡 𝑢𝑝𝑑𝑎𝑡𝑒𝑠 𝑎𝑛𝑑 𝑛𝑒𝑤𝑠 𝑎𝑏𝑜𝑢𝑡 𝐶𝑢𝑙𝑡𝑦𝑏𝑟𝑎𝑔𝑔𝑎𝑛 𝑎𝑛𝑑 𝑜𝑢𝑟 𝑜𝑡ℎ𝑒𝑟 𝑜𝑛𝑔𝑜𝑖𝑛𝑔𝑠.